RedSealCarpenterExam · Topics · Exam guide · Sample questions
Practice questions written by us, with the correct answer and the rule cited. They are not official questions.
1. When should the receiver tank of a portable air compressor be drained of condensed water?
Criterion A-1.01.10P of RSOS sub-task A-1.01 has the tank drained after use according to the manufacturer's specifications, which prevents corrosion of the tank and damage to tools. An annual inspection leaves water in the tank for months, a hose repair has no bearing on condensation, and a safety-valve release signals a fault rather than a draining schedule.
2. Which heading of a safety data sheet gives the conditions for safe storage of an adhesive, including incompatibilities?
The heading Handling and storage in Schedule 1 to the Hazardous Products Regulations covers precautions for safe handling and the conditions for safe storage, including incompatibilities (RSOS sub-task B-5.03). Disposal considerations deal with discarding the product, transport information with shipping, and regulatory information with the rules that apply to it.
3. A straight foundation wall is 9.5 m long, 2.4 m high and 250 mm thick on a metric job, and 30 ft. long, 8 ft. high and 10 in. thick on an imperial job. What concrete volume fills the wall form?
Volume equals length × height × thickness (RSOS sub-task C-8.04, concrete volume requirements): metric, 9.5 × 2.4 × 0.25 = 5.7 m³; imperial, 30 × 8 × (10 ÷ 12) = 200 cu. ft., and 200 ÷ 27 = 7.4 cu. yd. The smallest pair slips the decimal point in the thickness (0.025 m and 0.083 ft.). 57 m³ and 22.2 cu. yd. use wrong conversion factors (250 mm ÷ 100, and cubic feet ÷ 9 instead of ÷ 27), and 5 700 m³ and 200 cu. yd. leave a conversion out (the thickness kept as 250, and the cubic feet never divided by 27).
4. What minimum undamaged depth must remain when a hole is drilled through a loadbearing wall stud that is not reinforced?
Article 9.23.5.3. of the NBC (NBC 2020 and 2025) says the undamaged portion of a loadbearing stud must be at least two-thirds of its depth, unless the weakened stud is reinforced (RSOS sub-task D-12.02). The 40 mm value belongs to non-loadbearing studs and does not apply to a loadbearing stud. One-half and one-third would leave a stud too weak to carry its load.
5. How is the underlay laid on a roof before asphalt shingles are installed?
Sentence 9.26.6.2.(1) of the NBC (NBC 2020 and 2025) has underlay installed parallel to the eaves with head and end laps of at least 50 mm (RSOS sub-task E-15.01). Strips run up the slope would let water run along the joints, a 25 mm lap is half of the required lap, and butted joints do not provide the lap that sheds water.
6. How are tongue-and-groove wood boards nailed so that the nail heads are hidden?
Blind nailing is done through the tongue at an angle into each support, and the next board's groove covers the nail head (RSOS sub-task F-17.03, secure solid wood finishes with fasteners). Face nails and staples show on the finished surface and need filling. Nails through the groove edge with the heads left standing out would stop the next board from seating.
7. Where the side of a new roof slope runs along an existing wall that rises above it, what keeps water out of the joint?
RSOS sub-task G-22.01 requires exterior components such as flashing and cladding to be installed so that the transition from new to existing is weatherproof. Step flashing is lapped under the wall's membrane and over each shingle course, so water runs onto the roof and not into the joint. Caulking alone ages and cracks, cladding carried onto the shingles traps water, and a flat strip of felt sends water behind the shingles.
8. A carpenter attends a morning safety meeting where a new delivery route is announced. What should the carpenter do with the information afterward?
RSOS sub-task A-4.01 expects meetings to be attended, the information relayed to the workforce and then applied. Keeping it private or waiting for a notice delays the change and leaves absent workers unaware of the route. Mentioning it only by chance does not make sure that everyone receives it.
9. Where is the best place to stage a delivery of framing lumber on a tight site?
RSOS sub-task B-6.02 sets up storage by considering accessibility, crane location, the safety of workers and security. Level, drained ground near the work meets those needs. Low ground collects water, blocking the access road stops deliveries and traffic, and loading the edge of an excavation can cause a collapse.
10. Which sequence is correct when setting a precast panel on its bearing?
RSOS sub-task C-9.04 has the precast components aligned, shimmed and braced, and the crane must hold the panel until it is stable. Releasing the hook before bracing leaves an unsupported panel that can fall. Bracing before the panel is on its shims cannot work, and aligning the panel after the hook is released leaves no way to move it safely.
11. How is a long-span engineered truss lifted by crane without bending it sideways?
Correct answer: Lift it upright at the pick points on the top chord, using a spreader bar. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
12. After wind-driven rain, water shows at the lower corners inside a window. The sill membrane was lapped over the jamb membrane. What is the likely cause?
Correct answer: The sill membrane is reverse lapped, so water runs behind it. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
13. How are treads and risers secured in a housed stringer?
Correct answer: Slide them into the routed housings and tighten them with glued wedges. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
14. An exterior wall is left open overnight and rain is forecast. How is the opening covered?
Correct answer: Tarp fixed above the opening and lapped over the wall below. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
15. How many numbered headings must the safety data sheet of a solvent-based adhesive have under the Hazardous Products Regulations?
Correct answer: 16 headings, in a fixed order. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
16. To mark the plumb cut of a common rafter on a 6 in 12 roof, a carpenter draws along the tongue of a framing square set on the edge of the stock. Where are the numbers set?
Correct answer: 6 in. on the tongue and 12 in. on the blade. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
17. What sets the order and timing of form removal on a project?
Correct answer: The stripping schedule in the specifications. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
18. How are floor joists supported when they are framed into the side of a wood beam?
Correct answer: On joist hangers or on ledger strips nailed to the beam. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the National Building Code article it is based on.
19. Which tool is best suited to cut hinge gains in the edge of an exterior door slab?
Correct answer: Router with a hinge-mortising template. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
20. How is solid wood strip flooring acclimatized before installation?
Correct answer: Store it in the building at normal service conditions until its moisture content stabilizes. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
21. Which step comes first when planning the removal of materials in an older house?
Correct answer: Assess the existing structure for hidden conditions. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
22. What is the correct way to keep a straight ladder from shifting while workers climb it?
Correct answer: Tie it off at the top and set the feet on firm ground. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
23. Which layout structure gives a fixed point of known elevation that grades are measured from on a site?
Correct answer: A benchmark. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
24. What is used to identify the lifting points on a precast concrete panel?
Correct answer: The engineered drawings and specifications. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
25. Why is a gap left between the decking boards when they are installed?
Correct answer: To let water drain and allow the boards to move with moisture. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
26. Vinyl panels are cut to fit into J-channel on a cool day. How are the panel ends set?
Correct answer: Set with the gap the maker specifies for the air temperature. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
27. A new interior window is to be set in an opening whose sill is slightly out of level. How should the carpenter set the unit?
Correct answer: Shim the sill until the unit is level, then check plumb and square. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
28. What is the purpose of a void form placed under a grade beam?
Correct answer: To leave a gap so frost heave cannot lift the beam. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.
29. An exterior wall of sheet steel studs has an opening 3 000 mm (9 ft. 10 in.) wide. How are the studs framed at each side of the opening?
Correct answer: Three studs fastened together to act as a single unit. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the National Building Code article it is based on.
30. How are I-joists kept from rolling over before the subfloor panels are installed?
Correct answer: Fasten temporary bracing across the top flanges and tie it off. Premium access includes the full explanation (why this answer is right and why the other options are wrong) and the RSOS sub-task it is based on.