What this topic covers
Major Work Activity C of the RSOS Carpenter 2022, Performs concrete work, accounts for 16 questions out of 100: task C-8 Constructs formwork (12) and C-9 Installs concrete, cement-based and epoxy products (4). These are original study notes, not documents of the Red Seal Program, the CCDA, ESDC or any province. Code values refer to the National Building Code of Canada 2020, the edition supplied at the exam; a value that changes in the NBC 2025 is given with both editions. Health and safety rules and CSA standards vary by province and manufacturer: work according to jurisdictional regulations and manufacturers' specifications.
Shoring, underpinning and falsework
- Underpinning: built under an existing structure to keep its structural integrity; underpinning, shoring and bracing must keep an adjoining building from moving (RSOS sub-task C-8.01; Article 8.2.2.2. of the NBC, NBC 2020 and 2025).
- Falsework: a mud sill spreads the weight, base jacks level, bracing ties the legs; fasteners such as double-headed nails allow easy dismantling; shores stay until the concrete reaches the strength the engineer specifies (RSOS sub-task C-8.02).
Footing, wall and grade beam forms
- Keyway: the wall concrete fills the key, which resists sliding between wall and footing (RSOS sub-task C-8.03).
- Sequence: check the benchmark, mark the stakes from it, fasten the boards to the marks, brace last (RSOS sub-task C-8.03). Footing widths in Article 9.15.3.4. of the NBC change in the NBC 2025.
- Form ties: a snap tie breaks off inside the wall, a taper tie is pulled out from its large end, a coil tie leaves its coil anchor, a she-bolt leaves its inner rod (RSOS sub-task C-8.04).
- Lateral pressure: rises with the rate of filling; warmer concrete and thin lifts lower it; closer ties share it but do not reduce it (RSOS sub-task C-8.04).
- Grade beams: sleepers and void forms underneath allow for frost heave (RSOS sub-task C-8.04).
Slabs, columns, stairs and embedded items
- Slab on ground: at least 75 mm thick, not counting any topping (Article 9.16.4.3. of the NBC); 100 mm is the granular layer beneath (Sentence 9.16.2.1.(1) of the NBC), NBC 2020 and 2025 (RSOS sub-task C-8.05).
- Suspended slabs: other trades place conduit and inserts in sequence before the pour (RSOS sub-task C-8.05).
- Columns: braced in several directions; the rebar cage carries no form load (RSOS sub-task C-8.06).
- Stairs: a sloped riser gives room at the nosing and lets the tread be trowelled to its edge (RSOS sub-task C-8.07).
- Reinforcement: chairs hold the bars at the specified height for cover; bars are cleaned, never coated with release agent (RSOS sub-task C-8.08).
- Stripping: scrape and sweep the forms, then apply release agent (RSOS sub-task C-8.09).
Concrete volume
- Method: V = π × r² × h with π = 3.14, radius not diameter, times the number of pieces, times the waste factor; 27 ft.³ = 1 yd.³. Eight columns, r = 0.3 m (1 ft.), h = 3.0 m (10 ft.), 4% waste: 0.848 m³ × 8 × 1.04 = 7.05 m³; 31.4 ft.³ × 8 × 1.04 = 261.2 ft.³, or 9.7 yd.³ (RSOS sub-task C-8.06).
Placing, curing and finishing
- Testing: the slump test measures the consistency of fresh concrete (RSOS sub-task C-9.01).
- Blowout: deformation, leakage or noise means stop the pour and reinforce the form (RSOS sub-task C-9.01).
- Cold weather: below 5°C air, keep the concrete at 10°C or more for 72 h; 25°C is the upper limit while mixing and placing (Article 9.3.1.9. of the NBC, NBC 2020 and 2025; RSOS sub-task C-9.02).
- Curing compound: applied right after finishing, once the sheen has gone (RSOS sub-task C-9.02).
- Bleed water: wait; no dry cement to absorb it (Article 9.16.4.1. of the NBC; RSOS sub-task C-9.03).
- Precast: align, shim and brace before the crane releases the panel (RSOS sub-task C-9.04).
Sample questions (10)
1. What is the purpose of underpinning placed beneath an existing foundation next to a deeper excavation?
- To keep groundwater from entering the new excavation
- To raise the existing floor to match the new finished grade
- To hold back the soil face while the footings are formed
- To carry the building loads on a deeper bearing level
RSOS sub-task C-8.01 covers underpinning built under an existing structure to maintain its structural integrity, and Article 8.2.2.2. of the NBC (NBC 2020 and 2025) calls for adequate underpinning, shoring and bracing so an adjoining building does not move. Dewatering deals with groundwater, shoring holds back the soil face, and underpinning does not change the level of the existing floor.
2. How is underpinning placed under a long existing foundation wall so that the wall stays supported?
- Excavate the corners first, then remove the soil along the wall between them.
- Excavate and fill adjacent sections, starting at one end and moving along the wall.
- Excavate the full length of the wall, then fill the trench in one operation.
- Excavate and fill every second section, then return to fill the sections between.
RSOS sub-task C-8.01 includes the procedures to place underpinning, and the accepted practice is to work in alternating sections so the unexcavated sections keep carrying the wall while each new section cures. Working through adjacent sections undermines the wall right beside concrete that has not yet cured, while opening the whole length or the soil between the corners leaves long stretches of the wall without support underneath.
3. What should be done to timbers and other shoring materials before they are installed in an excavation?
- Coat them with form release agent so they can be pulled out later.
- Cut them to one standard length so the bracing is uniform.
- Inspect them for cracks, rot and damage that reduce strength.
- Soak them in water so the wood swells tight against the soil.
RSOS performance criterion C-8.01.03P requires shoring materials to be inspected for structural integrity before use. Release agent belongs on concrete forms, not on shoring, members are cut to the lengths the conditions and drawings need rather than to one length, and soaking does not improve contact with the soil or restore lost strength.
4. A crack gauge on an adjoining building beside a shored excavation shows the crack widening each day. What should the crew do first?
- Fill the crack with grout and continue excavating to the planned depth.
- Remove some of the shoring to take the pressure off the wall.
- Pile the excavated soil along the edge to support the wall.
- Stop work nearby and report it so the shoring can be reviewed.
A widening crack means the neighbouring structure is moving, which Article 8.2.2.2. of the NBC (NBC 2020 and 2025) requires shoring and underpinning to prevent (RSOS sub-task C-8.01). The crew stops and reports so the support can be reviewed. Grouting hides the movement, removing shoring removes support, and piling soil at the edge adds load to the wall.
5. What is the purpose of a mud sill placed under the base jacks of a falsework tower?
- To spread the tower load over more ground so it does not settle
- To tie the legs of the tower together against sideways movement
- To keep the base plates clean of mud and fresh concrete
- To bring the first frame level with the top of the footing
RSOS performance criterion C-8.02.04P calls for a mud sill that distributes weight, and C-8.02.02P requires the ground support to prevent settling and movement of the structure. Levelling is done with the base jacks, bracing ties the legs together, and keeping the plates clean is not the job of a sill.
6. When can the shores under a suspended concrete slab be removed?
- Once the slab surface is hard enough to walk on without marking
- After the same number of days that was used on the last pour
- After the concrete reaches the strength set by the engineer
- As soon as the concrete has taken its final set and gone hard
RSOS performance criterion C-8.02.09P says falsework is removed in sequence after the concrete has achieved the desired strength set by the specifications, which include the engineer's. A surface hard enough to walk on and the final set only show early hardening, and a day count copied from another pour ignores the mix, weather and loads of this slab, so none of them confirms the required strength.
7. Which fastening method suits falsework components that must be dismantled easily?
- Construction adhesive applied between the contact faces
- Common nails driven flush and the points clinched over
- Double-headed nails with the heads left proud of the lumber
- Screws driven flush with a thread-locking compound
RSOS performance criterion C-8.02.07P requires components to be secured with fasteners that allow easy dismantling, and the listed fasteners include nails, threaded rods and ties. Double-headed nails leave a head to grip with a bar. Clinched nails, adhesive and locked screws are all hard or impossible to take apart without damaging the members.
8. Why is re-shoring installed under a slab after the original shores have been removed?
- To bring the slab up to the specified elevation after stripping
- To carry construction loads until the concrete has enough strength
- To keep the form panels from sticking to the concrete
- To replace the mud sills once the ground has settled
RSOS performance criterion C-8.02.08P says falsework is re-shored according to the specifications until the concrete has achieved the desired strength. Re-shores do not change the slab elevation, they have nothing to do with form release, and the mud sills stay under the shores regardless of ground settlement.
9. What is the purpose of a keyway formed in the top of a footing?
- To lock the wall to the footing against sliding
- To let water drain away from the base of the wall
- To hold the reinforcing steel at the correct height
- To support the wall form while it is being plumbed
A keyway is one of the footing form components listed in RSOS sub-task C-8.03. The concrete wall fills the key and the key resists sliding between the wall and the footing. It does not drain water, rebar is held by chairs or supports, and the wall form is braced separately.
10. Which tool sets the top edge of footing forms in an excavation to elevation from a benchmark?
- A laser level or builders' level
- A framing square held on the grade stakes
- A chalk line snapped between the stakes
- A plumb bob hung from a string line
RSOS performance criterion C-8.03.03P determines footing elevations with layout tools and benchmarks, and the listed layout tools include laser levels and builders' levels. A plumb bob gives a vertical line, a framing square gives a right angle, and a chalk line gives a straight line but no elevation.