RedSealCarpenterExam

🏗️ Framing

What this topic covers

Major Work Activity D, Performs framing, accounts for 20 of the 100 questions: Task D-10 floor systems (6), Task D-11 deck systems (3), Task D-12 wall systems (6) and Task D-13 roof and ceiling systems (5). These are original study notes, not documents of the Red Seal Program, the CCDA, ESDC or any province. Code values refer to the National Building Code of Canada 2020, the edition supplied at the exam; a value that changes in the NBC 2025 is given with both editions; nailing, subfloor, stud and bracing figures change and are not quoted here. Health and safety rules and CSA standards vary by province and manufacturer: work according to jurisdictional regulations and manufacturers' specifications.

Engineered floors

Dimensional lumber floors

Decks

Wall systems

Roof and ceiling systems

Take the free test · full question bank and mock exams with a subscription

Sample questions (10)

1. What is the minimum length of end bearing for a floor joist that rests on a wall plate?

  1. 38 mm (1 1/2 in.)
  2. 19 mm (3/4 in.)
  3. 64 mm (2 1/2 in.)
  4. 89 mm (3 1/2 in.)

Sentence 9.23.9.1.(1) of the NBC (NBC 2020 and 2025) sets the minimum end bearing of floor joists at 38 mm, except when they are carried on a ribbon board. 19 mm is too short to bear safely, while 64 mm exceeds the requirement and 89 mm is the minimum end bearing of a beam under Article 9.23.8.1. of the NBC. Bearing length is part of installing floor members in RSOS sub-task D-10.02.

2. Header joists around a floor opening must be doubled when they exceed what length?

  1. 1.2 m (3 ft. 11 in.)
  2. 2 m (6 ft. 7 in.)
  3. 3.2 m (10 ft. 6 in.)
  4. 800 mm (2 ft. 7 in.)

Sentence 9.23.9.5.(1) of the NBC (NBC 2020 and 2025) requires header joists around a floor opening to be doubled once they exceed 1.2 m. The 3.2 m figure is the header length above which the header size is calculated (Sentence 9.23.9.5.(2) of the NBC), while 2 m and 800 mm apply to the trimmer joists: above 2 m of header the trimmer size is calculated, and above 800 mm the trimmers are doubled (Article 9.23.9.6. of the NBC). These openings are framed under RSOS sub-task D-10.02.

3. What determines the size and location of the holes permitted in the web of an I-joist?

  1. The one-quarter depth limit used for sawn-lumber joists.
  2. The hole chart supplied by the I-joist manufacturer.
  3. The span table for dimensional lumber joists in the code.
  4. The thickness of the OSB subfloor laid over the joists.

RSOS sub-task D-10.01 requires engineered components to be installed according to the manufacturers' specifications, and each manufacturer publishes a chart that limits the size and position of web holes. The one-quarter depth rule of Article 9.23.5.1. of the NBC (NBC 2020 and 2025) applies to sawn joists, not to I-joists. Span tables for dimensional lumber do not cover engineered products, and the subfloor thickness has no bearing on web openings.

4. Why is a web stiffener fastened to an I-joist where a concentrated load bears on the top flange?

  1. To carry the load into the web so it does not buckle.
  2. To brace the joist against rolling over along its span.
  3. To stop the web from shrinking as the subfloor dries out.
  4. To raise the I-joist so that it matches the sawn joists.

RSOS sub-task D-10.01 lists web stiffeners among the components of an engineered floor, and manufacturers call for them under concentrated loads above the limit set in their specifications, so that the load passes from the flange into the web without buckling it. A stiffener does not change the joist depth, a short block fixed at one point cannot brace the joist along its span, and it does not control the moisture movement of the web.

5. How are small ducts or pipes passed through an open-web floor truss?

  1. Cut one web member and sister it with a short piece of lumber.
  2. Drill the bottom chord at mid-span where the stress is low.
  3. Run them through the open spaces between the web members.
  4. Notch the top chord near the bearing and cap it with a strap.

Open-web floor trusses are designed with openings between the web members for services, and RSOS sub-task D-10.01 requires installation according to the manufacturer's specifications. Drilling or notching the chords, or cutting a web member and sistering it, changes the truss design and is not done without the approval of the truss designer.

6. How are the plies of a multi-ply LVL beam fastened together?

  1. With the same double row of nails used for sawn-lumber beams.
  2. With a continuous bead of adhesive and no mechanical fasteners.
  3. With a pair of bolts placed one near each end of the beam.
  4. With the fasteners and spacing in the manufacturer's schedule.

RSOS sub-task D-10.01 requires beams to be built and installed according to drawings, specifications and codes, and for LVL the specification is the manufacturer's schedule of fastener type, size and spacing for the load carried. The nailing pattern of Article 9.23.8.3. of the NBC (NBC 2020 and 2025) is written for built-up sawn lumber, adhesive is not a substitute for fasteners, and two end bolts leave the middle of the plies unconnected.

7. A cantilever of sawn floor joists carrying a roof load has tail joists at right angles to the main joists. How are the tail joists laid out?

  1. Extend them back at least 2 times the cantilever, to a doubled header.
  2. Extend them back at least 6 times the cantilever, to a single header.
  3. Extend them back at least 6 times the cantilever, to a doubled header.
  4. Extend them back at least 3 times the cantilever, to a single header.

Sentence 9.23.9.9.(3) of the NBC (NBC 2020 and 2025) requires the tail joists of such a cantilever to extend back at least six times the cantilever length and to be end nailed to an interior doubled header. A multiple of two or three is too short to resist the overturning effect, and a single header is not the doubled one that the Sentence calls for. Cantilevered sawn joists and their framing practices are covered by RSOS sub-task D-10.02.

8. How is the crown of a sawn floor joist placed when the joist is installed?

  1. Alternate crown up and crown down to even out the floor.
  2. Crown down, so the bow flattens under the floor load.
  3. Crown up, so the bow can be planed flat after framing.
  4. Crown up, so the bow flattens under the floor load.

RSOS sub-task D-10.02 requires floor members to be installed considering crown placement. The crown, the slight bow along the edge, goes up so that the floor load tends to straighten the joist. Crown down lets the bow grow into a sag, planing a joist removes the depth it needs, and alternating the crowns leaves some joists sagging under the floor.

9. Which condition is a reason to reject a sawn floor joist during inspection?

  1. A slight crown along the length of the joist.
  2. Decay found along the bottom edge of the joist.
  3. A grade stamp placed near one end of the joist.
  4. Tight, sound knots near the middle of the face.

Defects named in RSOS sub-task D-10.02 include unsound knots, wane, splits, rot, decay and mould, and decayed wood has lost strength, so the joist is rejected. A slight crown is normal and is placed up, sound knots are accepted within the grade, and a grade stamp is the expected mark of an inspected piece.

10. How are tail joists supported where they frame into a doubled header around a stairwell opening?

  1. Toe-nail each one to the header from below with one nail.
  2. Rest each one on a strip of plywood glued to the header.
  3. Hang them on joist hangers or nail them as the code requires.
  4. Butt each one to the header and rely on the subfloor.

Article 9.23.9.7. of the NBC (NBC 2020 and 2025) requires tail joists carried by the floor framing to be held by suitable joist hangers or by nailing as set out in the code's nailing table. A single toe-nail, a glued plywood strip and the subfloor alone are not recognised supports for the joist ends, and RSOS sub-task D-10.02 requires rough openings to be framed according to codes.

Start free

RedSealCarpenterExam · Topics · Exam guide · Sample questions