Major Work Activity G of the RSOS Carpenter 2022, Performs renovations, accounts for 10 questions out of 100: task G-21 Performs renovation-specific support activities (5) and G-22 Performs renovation-specific construction activities (5). These are original study notes, not documents of the Red Seal Program, the CCDA, ESDC or any province. Code values refer to the National Building Code of Canada 2020, the edition supplied at the exam; a value that changes in the NBC 2025 is given with both editions. Health and safety rules and CSA standards vary by province and manufacturer: work according to jurisdictional regulations and manufacturers' specifications.

Assessing before removal

Removal and waste

Protecting the structure and people

Joining new to existing

Changing the structure

Take the free test · full question bank and mock exams with a subscription

Sample questions (10)

1. What should a carpenter do on finding material that may contain asbestos while stripping a wall?

  1. Wet the material and keep removing it with hand tools.
  2. Stop work in the area and have the material assessed.
  3. Bag the material with the regular job-site waste.
  4. Tape plastic over it and carry on stripping nearby.

RSOS sub-task G-21.01 has suspected hazardous substances such as asbestos reported, then abated and contained under the applicable standards and regulations. The carpenter therefore stops work in the area and has the material assessed under the rules of the jurisdiction. Carrying on with removal, even with the material wetted, disturbs it before it is assessed, bagging it with ordinary waste mixes hazardous waste with regular waste, and plastic taped over it does not protect workers who keep stripping nearby.

2. How should reusable trim and doors be taken out of a room that is being renovated?

  1. Cut them out in pieces to speed up the removal work.
  2. Pry them off carefully, label them and store them dry.
  3. Pull them off with a bar and stack them outdoors.
  4. Break them loose and sort the pieces after the job.

RSOS sub-task G-21.01 has the carpenter identify materials that may be reclaimed and reused, then remove them so that they can be sorted for reuse. Careful prying avoids splits, and labelling and dry storage keep the parts matched and usable. Cutting, rough pulling or breaking items loose damages them, and leaving them outdoors or sorting them after the job lets them be spoiled or mixed with waste.

3. What must be done before an interior wall is opened up for removal?

  1. Locate and isolate any electrical, gas or plumbing lines in it.
  2. Cut the studs at mid-height to weaken the wall first.
  3. Strip the floor finish back to the subfloor on both sides.
  4. Remove the top plate so the ceiling framing is released.

RSOS sub-task G-21.01 has the carpenter assess the structure and remove components in a safe sequence, which includes finding the services run through the wall. Electrical, gas and plumbing lines are identified and shut off or isolated, by the qualified trade where required, before cutting so that they are not struck or left live. Cutting studs or the top plate weakens the framing before the wall is proven, and removing the floor finish does nothing to protect the services.

4. Which method of assessing an existing wall is non-destructive?

  1. Cutting an inspection opening in the wallboard
  2. Visual inspection backed by a thermal camera
  3. Taking a core sample from a framing member
  4. Removing a strip of siding to expose sheathing

RSOS sub-task G-21.01 expects the carpenter to know destructive and non-destructive methods of assessing an existing structure. A visual inspection with a thermal camera leaves the wall intact. Cutting an opening, taking a core sample from framing and removing siding all damage the assembly and must be repaired afterwards, so they are destructive.

5. How should debris be brought down from an upper storey during demolition work?

  1. Drop it from a window onto a fenced pile below.
  2. Send it down an enclosed chute to a container.
  3. Throw it over the edge into a roll-off bin.
  4. Slide it down a loose sheet of plywood to the ground.

RSOS sub-task G-21.01 requires removed components to be sorted and disposed of according to regulations. Article 8.2.5.1 of the NBC (NBC 2020 and 2025) does not allow waste to fall freely from one storey to another, and Article 8.2.5.2 names containers, an enclosed chute or a hoisting apparatus as the means of removal. Dropping debris from a window or throwing it over the edge is free fall, and sliding it down a loose sheet of plywood is uncontrolled, so all three endanger the people below.

6. While stripping plaster from an old exterior wall, a carpenter finds a soft, dark, musty sill plate. What is the correct response?

  1. Fill the soft wood with filler and paint it to seal the surface.
  2. Spray the plate with disinfectant and close the wall back up.
  3. Find and stop the moisture source, then replace the damaged wood.
  4. Replace the plaster and let the wood dry out by itself.

RSOS sub-task G-21.01 lists rot and mould among the conditions the carpenter must assess and report. Soft, dark, musty wood is a sign of decay caused by moisture, so the water source has to be found and stopped and the damaged members replaced. Filling and painting, spraying and closing up, or replacing the plaster alone hide the problem, leave decayed wood in the wall and let the damage return.

7. Which tool is best for cutting through nails hidden in framing during selective removal?

  1. Reciprocating saw with a bi-metal blade
  2. Jigsaw with a fine wood-cutting blade
  3. Hand rip saw with a coarse tooth pattern
  4. Circular saw with a combination blade

RSOS sub-task G-21.01 has the carpenter select tools suited to the job and to the manufacturers' specifications. A reciprocating saw with a bi-metal blade cuts wood and nails together when members are cut apart for removal. A circular saw, a jigsaw with a wood blade and a rip saw are dulled or damaged by nails and are awkward in the tight cuts of selective removal.

8. When is temporary shoring installed for the opening of a bearing wall?

  1. As soon as the old wall has been taken down
  2. After the first studs are cut to relieve the load
  3. Once the new lintel has been set in the opening
  4. Before any load-carrying part of the wall is cut

RSOS sub-task G-21.02 has the carpenter construct and install temporary supports according to the loading conditions and drawings. The supports must already carry the load before anything in the bearing wall is cut, otherwise the floor or roof above sags or drops. Installing them after studs are cut, after the lintel is set or after the wall is down is too late, because the load has already been released.

9. How is temporary shoring usually arranged when a wall carrying the floor above is opened?

  1. A single post at the centre of the opening, under one joist
  2. Jacks on the finished floor with no plate or beam above them
  3. A temporary stud wall on each side, tight to the joists above
  4. Diagonal braces nailed from the wall to the floor above

RSOS sub-task G-21.02 lists temporary supports such as posts, beams and pipe jacks, located according to the loading conditions and drawings. A temporary stud wall on each side, with its top plate wedged snug under the joists, carries the load evenly and leaves room to work. A single post, bare jacks on the finished floor or diagonal braces on the wall concentrate the load or fail to carry it.

10. What protects a finished hardwood floor along a route used to carry materials through the house?

  1. A thin plastic film laid loose over the boards
  2. A thin cotton sheet laid flat on the boards
  3. Plywood or heavy cardboard laid over the floor
  4. A rubber mat placed under each tool box

RSOS sub-task G-21.02 lists finished floors among the areas protected by coverings such as drop cloths, plywood and cardboard. A rigid layer of plywood or heavy cardboard spreads the load and resists dragged tools. A thin film, a thin sheet or a mat under the tool boxes does not stop the scratches and dents caused by boots, carts and dropped material.

Start free